THE CHALLENGE:
To provide our customer, a leading trucking accessories supplier, with complete design build of an under running 5 ton overhead crane system. The job incorporated the 5 ton overhead crane system and (2) ½ ton jib cranes.

SPECIAL CONSIDERATIONS:
The general contractor needed design build capabilities for the overhead crane and runway system. Crane-Tec provided complete design of the under hung runway system incorporated into the general contractors special overhead crane truss system.

OUR TEAM APPROACH:
Our engineers, armed with building drawings, determined runway steel and hanger design. Engineered drawings with overhead crane loads were submitted to the general contractor for approval. Crane-Tec’s experienced field crew installed the complete system and jib cranes in under 3 days to meet the G.C.’s demanding schedule.

RESULTS:
The general contractor maximized the strength
of the building, Crane-Tec supplied a turn key
overhead crane system and the owner maximized floor space. The overhead cranes were ready ahead of schedule allowing the owner to set up manufacturing machinery with the use of the overhead crane.

 